Note : This form is designed for general use and may not be exhaustive. Modifications and additions may be necessary to suit individual projects and to address specific environmental issues and associated mitigation measures. Project contract no. CV/2006/01 Site Location : Stanley Bay Project : Construction stage / status during inspection : Inspection Date : Inspected by :
Phase 1 – Drainage & Road works
25 January 2006 Inspection Time : CY Tam (Project Environmental Engineer) Weather : Remarks
Implemented? Inspection Items
Air Pollution Control
1.1. Are the construction sites watered to minimize dust generated? 1.2. Are stockpiles of dusty materials (size with more than 20 bags cement) covered or watered? 1.3. Cement debagging process undertaken in sheltered areas 1.4. Are all vehicles carrying dusty loads covered/watered over prior to leaving the site? 1.5. Are demolition work areas watered? (e.g. trimming activities by using breaker) 1.6. Are dusty roads paved and/or sprayed with water? 1.7. Are dust controlled during percussive drilling or rock breaking? 1.8. Are plant and equipment well maintained? (any black smoke observed, please indicate the plant/equipment and location) 1.9. Is dark smoke controlled from plant? 1.10. Are there enclosures around the main dust-generating activities? (e.g. grout mixing) 1.11. Hoarding (not